BIỆN PHÁP THI CÔNG
CONSTRUCTION METHODS
WORK: RENOVATION OF NSX2-NSX3 BMSG VENTILATION SYSTEM
Address: 240 Hau Giang, Ward 9, District 6, Ho Chi Minh City
A/ TỒ CHỨC THI CÔNG CHUNG
GENERAL CONSTRUCTION ORGANIZATION
1. Quản lý chung của Công ty:
General management of the Company:
All installation activities at the construction site are placed under the close inspection and supervision of Trung Nguyen Company and in coordination with Binh Minh Plastics Joint Stock Company.
Construction progress and methods meet Occupational Safety standards and Fire Prevention and Fighting must be approved by the Company before starting construction.
Trung Nguyen Company arranges the chief commander or technical commander at the construction site.
2. Tổ chức thi công ngoài hiện trường:
Construction organization of in the field:
2.1. Ban chỉ huy công trường.
Site Steering Committee.
Đại diện Công ty:
Representative of the Company:
Engineer: NGUYEN HUU QUAN - Site commander
Chi huy công trường: Đại diện cho nhà thầu ở công trường, có trách nhiệm điều hành toàn bộ dự án - điều tiết các công nhân thi công về tiến độ và trao đổi với chủ đầu tư để giải quyết các vấn đề về thi công
Site commander: Represent the contractor at the construction site, responsible for operating the entire project - regulating the construction workers on progress and communicating with the investor to solve construction problems
2.2. Kỹ thuật & công nhân:
Technicians & workers:
The technicians are constructing and installing the ventilation system.
Technicians comply with construction methods to ensure occupational safety - fire protection
A team of highly skilled technicians with sufficient numbers to participate in the construction of the works is assigned to the construction site to keep up with the construction schedule from time to time.
3. Bố trí mặt bằng thi công:
Layout of construction site:
Arrange the total construction site based on the total installation site, the order of construction of the proposed items with paying attention to the requirements and regulations on construction safety, environmental sanitation, dust-proof, noise-proof, fire-proof, security, ensuring that it does not affect the operation of surrounding areas.
Electricity for construction: Coordinate with the investor to take the existing power source of the plant, install anti-shock CB and carry out grounding with the plant system.
All waste in daily life and construction is collected, transported, and dumped to the right place to ensure general hygiene and aesthetics of the construction site.
B/ BIỆN PHÁP KIỂM SOÁT CHẤT LƯỢNG:
QUALITY CONTROL MEASURES:
Materials put into the works:
The materials put into the work must be approved by the investor, and compared with the quotation before being put into installation.
2. Các quy phạm kỹ thuật áp dụng:
Applicable technical regulations:
To ensure the construction of work items in accordance with technique, fine arts, and reduce defects, the contractor sets out a Process to perform and check each of the following jobs:
The technical department of the investor shall coordinate with the Site Steering Committee to consider and check the drawings (if any) or based on the quotation to carry out the construction.
If the drawings are found to be defective, unreasonable or the components need to be implemented in detail, it’s required to set out a direction to handle the defects and submit them to the investor and design consultant for consideration and handling.
Before moving to construction, the contractor will conduct internal inspection and acceptance.
After the internal inspection and acceptance is completed, the acceptance will be conducted with the Investor.
C/ BIỆN PHÁP THI CÔNG CHI TIẾT CỦA CÔNG TRÌNH:
DETAILED CONSTRUCTION METHODS OF THE WORK:
1/ Nhân lực thi công:
Construction manpower:
Installation mechanician: 04 employees
Electrical construction staff: 02 employees
Staff in charge of supervision: 01 employee
2/ Quy trình thi công:
Construction process:
2.1/ Lắp đặt dây cứu sinh:
Installation of lifeline:
The installation of the blower on the roof of the factory does not have an existing lifeline system, leading to a high risk of falling. To ensure the safety of workers during construction, the contractor must set up a temporary lifeline system on the roof for the construction area.
During the installation process, safety factors must be ensured when working at height. In setting up the temporary lifeline system, the contractor must discuss with the representative of the investor to come up with the optimal and safest method for the work.
2.2/ Lắp đặt miệng gió quạt hút áp mái:
Installation of rooftop exhaust fan vent-hole:
Installation of vent-holes, fans and equipment: Cut corrugated iron roof -> install vent-holes -> install edges around -> install brackets for ducts and fans -> install fans. During the construction process, staff must be always present to ensure the safe installation in accordance with technique, avoid dropping materials and debris to the bottom (the machine is in production).
Installation of the power supply for the fan: The installation staff has expertise in electrical installation, the power supply for the fan must be taken under the guidance of the investor, ensuring the power supply is sufficient to meet the quantity of equipment. Since the equipment is installed outdoors, the actual impact of weather on electrical safety must be assessed and remedial measures taken directly on site.
2.3/ Mô tả hệ thống thông gió NSX3-NSX3:
Description of the NSX3-NSX3 ventilation system:
Manufacturer 2 arranges 11 rooftop ventilation fans to suck out the factory heat
Manufacturer 3 arranges 12 rooftop ventilation fans to suck out the factory heat
Each workshop has its own electrical cabinet for automatic control (setting the time) or manually, and in each electrical cabinet, each fan can be turned on and off separately.
Information about the fan control cabinet.
Electrical cabinet cover 400*600*210mm made of 1.0mm-thick corrugated iron with electrostatic painting
Power supply cable for electrical cabinet/ Cadivi 3*4.0mm
Power supply cable for fan/ Cadivi 3*2.5mm
On/off switch for manual fan control
Time relay to control fan according to setting (optional)
Incoming circuit breaker for power supply to the system: CP Mitsubishi NF 63-CV 3P 50AP
Information on ventilation fan.
Indirect square fan 1000 - Model: QDW-1000.
Dimensions: 1000x1000x400 mm
Flow QMax=30,000 m3/h
Head H Max = 65 pa + Speed = 600 v/p
One side is net, and the other side is shutter.
Galvanized steel fan frame, ribbed 430 stainless steel blades.
Operating noise: 70-75 dB (measured at a distance of 2m)
2.3/ Thông số trao đổi gió:
Wind exchange parameters:
Tiêu chuẩn thông gió nhà xưởng là từ 40>60 lần/h theo tiêu chuẩn TCVN 5687: 2010.
Factory ventilation standards are from 40>60 times/h according to TCVN 5687: 2010.
X = 60: Number of air exchanges
Q = 30,000 m3/h: Wind flow of 1 fan (m3/h)
Calculation formula
Tg = X*T = 60*6,054.4 = 363,264m3/h
N = Tg/Q = 363,264/30000 à Number of fans = 12 units/factory (for Manufacturer 3)
Manufacturer 2 minus the space of 2 gables with working room: 11 fans are arranged
Bảng tính số quạt và độ ồn dựa trên tiêu chuẩn trao đổi gió TCVN 5687: 2010.
Calculation table of number of fans and noise level based on TCVN 5687: 2010 wind exchange standard
BẢNG TÍNH 1
CALCULATION TABLE 1
|
Số lần trao đổi gió Number of wind exchanges |
Số quạt Number of fans (b) |
Độ ồn Noise level |
Nhiệt độ giảm Temperature decrease |
Nhà SX2 Manufacturer 2 |
Nhà SX3 Manufacturer 3 |
|
20 lần/1h 20 times/hour |
|
Từ 75dbà 90db
|
|
4 cái 4 pieces |
5 cái 5 pieces |
|
40 lần/1h 40 times/hour |
|
Từ 80 db à 120db 80 db à 120db |
|
8 cái 8 pieces |
9 cái 9 pieces |
|
60 lần/1h 60 times/hour |
|
Từ 85 db à 130db 85 db à 130db |
|
11 cái 11 pieces |
12 cái 12 pieces |
Theo tiêu chuẩn trao đổi gió trong nhà xưởng sản xuất là 60 lần/h. Vậy theo bảng tính ta chọn dòng 3 cột F (12 cái/ nhà xưởng).
The standard of wind exchange in the factory is 60 times/hour, so according to the calculation table, we choose row 3 column F (12 pieces/factory).
Function of ventilation works: Create ventilation for the factory, the frequency of continuous exchange N=60 times/hour. The rooftop fan system forcibly sucks the "wind" from inside the full
factory and discharges it to the outside of the factory by the fan to create negative pressure for the "fresh air" to circulate into the factory.
2.4/ Vận hành chạy thử và nghiệm thu:
Commissioning and acceptance:
Operation of system
Power on for commissioning, the contractor self-checks and assesses product quality and noise level, if there are any shortcomings, it must be corrected and completed before inviting the investor to inspect and accept.
Temperature acceptance: Temperature sampling is carried out as follows:
Sampling before operation:
Use a temperature gauge to measure at the same time at 3 points chosen by the Investor and the contractor at the position in the middle of the factory with a height of about 3m from the floor of the factory divided into 3 intervals according to the length of the factory before operating the system and record the temperature parameters as a basis for checking the temperature difference.
Sampling after operation:
After operating the system for 20 minutes, the contractor will re-measure the temperature of the 3 initially measured positions. Then, compare the temperature difference before and after operation based on the following table
BẢNG TÍNH 2
CALCULATION TABLE 2
|
Nhiệt độ trước Previous temperature |
Nhiệt độ sau Following temperature |
Nhiệt độ chênh lệch Temperature difference |
Vị trí 1 Position 1 |
|
|
C = A - B |
Vị trí 2 Position 2 |
|
|
C = A - B |
Vị trí 3 Position 3 |
|
|
C = A - B |
Comparing the results of column (C) CALCULATION TABLE 2 and column (d) CALCULATION TABLE 1, the conclusions are as follows:
If C > d: Meet the set requirements, conduct acceptance and hand over to the Investor
If C < d: Not meet the set requirements, the contractor needs to find remedial measures to achieve the required parameters from CALCULATION TABLE 1
The above temperature acceptance measure is carried out by the contractor together with the investor's inspection.
2.5/ Hình minh họa: Quạt thông gió 1000x1000mm (mặt trước và mặt sau quạt)
Illustration: 1000x1000mm exhaust fan (front and back of fan)
2.4/ Hình ảnh minh họa điển hình của công trình khác
Typical illustrations of other works